Archive for July 12th, 2010
» posted on Monday, July 12th, 2010 at 12:08 by alpip
BP Gulf Oil Leak Well-Head Repair … an anthology III
Sunday morning (7/11/2010) finds the Flange Transition Spool (FTS) already hanging near the well head as preparations are underway to make the installation:
I am unsure what the tool is in the foreground. It was on screen in the shot above as I logged on Sunday morning and I didn’t notice it after a short while. Notice in this shot there are three ROVs … the lights off in the gloom to the right of the view, the glow of lights behind the mechanical arm (upper left) and the ROV holding the tool.
The image above shows the bottom flange, sans the old top flange removed in the early hours of the morning. Note to the right the white, inverted “u” dispersant injector has been reinserted directly into the well
The method BP is going to use to guide the FTS into the correct orientation above the well flange is through the use of tapered dowels that fit into holes in the flange made for that purpose. You can clearly see the dowels in the image below.
However, BP is using a clever way of making sure they are able to find the correct holes for the dowels. In the image on the left above, note the slim cables attached to the bottom of each tapered dowel; the ROV operator threaded each of these cables into the correct hole in the bottom flange prior to moving the FTS into position. By keeping tension on these cables, the FTS will be guided into the correct orientation even though the view will be blocked by the oil plume once the FTS is positioned within the plume.

Flange Transition Spool being moved into position adjacent to the well (click image to see an enlarged version)
The images above show two views as the Flange Transition Spool continues into position above the well.
BTW … I believe these two images are from ROVs controlled by another support vessel, the Boa Deep C, though I haven’t found that ship in the readily available information on BP’s site. These two ROV’s continue installing the FTS.
Above, the FTS getting closer to the well. The images below show the FTS in the plume, being positioned directly over the well. Note the tapered dowel and the cable being pulled taught by another ROV somewhere off camera.
In the next shots the FTS is in position and being lowered onto the well-head flange:
Things are looking good!

FTS almost in place
Just a litttttttle bit more to go ….
But it’s stuck. They take a closer look …
Okay … let’s try to raise it up slightly and then put it back down …
Okay … now lower it again and let’s see if it will seat itself:
Next, remove the external sleeves that held the bolts in place and begin screwing each into the lower flange.
Note the string attached to the white sleeve wrapped around each bolt … the ROV operator grabs the string and gives it a jerk and the sleeve pops off, allowing the bolt to fall all the way into the hole until it hits the threads.
As before with the removal of the bolts, the ROV operator places each of the removed sleeves onto a tray on the old BOP (blowout preventer)
Each bolt is then “hand” tightened:
At this point I had plans to visit some friends, so I left. When I returned, I wasn’t really sure what it was I was watching, but after a few minutes I guessed that another type of hydraulic socket tool was …
… torquing down the bolts. As you watched, the ROV camera would watch as the operator placed the tool on a bolt and then the view would switch to …
A pressure gauge. As you watched, the gauge would move from zero up to more than ….
… 6,000 PSI (pounds per square inch). The operator would drop the pressure then reapply several times before moving to the next bolt. It seems that the highest pressure reached on each bolt was around 6.600 PIS or so. I didn’t follow every step, but it appeared the operator torqued each blot at least twice. I’m not sure how many foot-pounds relates to 6.600 PSI, but I bet it’s more than what I used to torque the head bolts too on my 427 cubic inch Chevy I had in my flat bottom ski boat!
The last operation I watched last night was something I didn’t understand. An ROV holding some sort of an instrument moved to the base of the well casing where it came out of the sea floor …
The instrument was placed against the casing as shown in the image below …
The instrument was held in place for several minutes, then moved 90 degrees and the process repeated for a total of four times. My first thought was that it was some kind of ultrasonic flow measuring device, but the ones I’m familiar with require sensors on both sides of the pipe, and for such a large diameter pipe, the sensors would be much longer.
I then assumed the instrument was some sort of device that measured the stress on each quadrant of the casing to insure the added weight of the Flange Transition Spool wasn’t causing undue stress on the casing. However, when completed at the bottom of the stack, the ROV relocated to …
… the top of the stack and put the instrument directly into the oil plume! Some kind of flow measurement device?
Things began to slow down, so I called it a night. I’ll pick up with Monday morning’s activities in the next post.
post a comment | filed under Engineering · Environment · Oil | tags: BP, crude oil, engineering, Gulf Coast, Macondo well, oil spill, remotely operated vehicles, ROV
» posted on Monday, July 12th, 2010 at 10:18 by alpip
BP Gulf Oil Leak Well-Head Repair … an anthology II
So … last night we left off at the point where BP was removing the flange bolts using a hydraulic socket wrench.
Notice the bolt to the right of the one with the wrench (not the larger object directly adjacent to the bolt the socket is on … I believe that is an alignment pin, but certainly not a bolt head. I’m referring to the second object to the right of the bolt that the socket is on). It appears the flat surfaces have at some point been damaged. The image below provides a better view:
Not to worry! Just go to your trusty tool box and bring out the Dremal rotary tool … an industrial strength Dremal if I do say so!

Industrial strength Dremal rotary tool being used to grind burrs off of hex bolt in image on the left (click on image to see an enlarged version)
Below is a second view of the grinder seen from both ROV cameras:
The next image shows the hydraulic socket wrench loosening the now-cleaned bolt:
Same view as the last, but from both ROVs (note the polished surface … as a the result of grinding, of the bolt below the socket in the image from ROV 1):
ROV 1 now begins to remove all the loosened bolts:
The “hand” at the end of the arm is positioned directly above each bolt and then rotates counter-clockwise, unscrewing each bolt.
I was surprised that as each bolt was removed, the ROV would back away from the stack and move to a shelf located somewhere lower on the stack and drop each bolt on the shelf, rather than just drop the bolts to the ocean floor. Keep your work space tidy!!
Meanwhile, in the next image ROV 2 breaks out the trusty rotary wire brush and begins cleaning the surface of the outer flange:
It is pure speculation on my part, but I suspect that the Flange Overshot Removal Tool (FOLT), designed to remove the damaged flange, is designed with relatively close tolerances. BP cleaned the outside of the flange to make sure there are no large burrs or other obstacles on the flange that could inhibit the placement of the FOLT, shown below:
Wire brushing continues to clean the entire outer surface of the flange:
I mentioned the “tool box: earlier. Below is a shot of one of those tool boxes:
Note all the different colored rope loops with different tape markings; a very simple and clever way of identifying different tools IMHO. I’s say these guys may have done this type of thing once or twice before
Below is a second view of the same tool box:
At this point it’s almost midnight Saturday evening in the Gulf and the activity that I can see via the various ROV cameras is slowing down, so I decide to call it a day and go to bed. As it turned out, BP was apparently able to remove the flange around 12:30 or 12:45, so I missed that operation completely.
In the next post I’ll pick up the operation that began the next morning to install the Flange Transition Spool, seen in the image below:
post a comment | filed under Engineering · Environment · Oil · Technology | tags: BP, crude oil, engineering, Gulf Coast, Macondo well, off-shore drilling, oil spill, remotely operated vehicles, ROV


































